Where failure to achieve Completion by the Date for Completion occurs as a result of a Relief Event, the Date for Completion will be extended. Where there is a two-stage Completion process (for example, a Date for Technical Completion to be met prior to a Date for Commercial Acceptance), any such Relief Event will result in an extension to both of those dates.
Whether or not such an event results in an extension of the contract term (and therefore the operating term) will depend on the project specifics and whether there is any special need for the project to terminate at a particular time.