(a) Throughout the operating term, the private party must (at its own cost) provide the Contracted Services:
(i) in accordance with the Services Specifications (noting that the Services Specifications may, in part, require compliance with mandatory requirements of government for design and construction);
(ii) in a manner consistent with the asset management plan, the Output Specifications and the operating and quality assurance manuals that the private party is required to prepare for the project;
(iii) in accordance with industry best practice, all relevant policies and procedures and applicable Laws, approvals and specified quality and safety standards;38
(iv) so that the facility remains at all times during the operating term fit for its intended purposes (as described in Chapter 9 (Design)); and
(v) in coordination with the delivery by government of the core services and the contemplated possession and use of the facility by government (and so as not to disrupt government in the provision of the core services).
(b) The private party must warrant that it will at all times provide the resources, expertise and experience to maintain the facility and provide the Contracted Services in accordance with the above requirements.
___________________________________________________________________
38 Certain policies applicable to the project will be included in the Project Brief, but the private party will be expected to comply with all policies to which the project is subject.