If the auditor's written report shows an inaccuracy, incorrectness or incompleteness in the PMS or any performance data for, or resulting from, the PMS then the private party must:
(a) correct and re-issue the affected report or data and take steps to remedy the fault in its monitoring, measuring and reporting system; and
(b) if the error has affected the amount of a service fee, make the appropriate adjustment from the next scheduled service fee, or, if there is no further service fee scheduled, the amount will be a debt due and payable from the private party to government.