16.3.5 Acceleration

If the progress of the works is delayed by a Relief Event, government will have the option (at its cost) of requiring the private party to accelerate the works instead of extending time to the extent that this is physically possible.56




___________________________________________________________________

56  Compensation will be calculated in manner consistent with the principles set out in Chapter 18 (Compensation payable), whereby government will pay for the private party's incremental costs (but with no allowance for a profit margin by the private party).