(a) The service fee will not be abated for Service Failures caused by a Relief Event,57 except for costs not incurred by the private party during the Relief period and to the extent that the Relief Event or any risk that caused the Relief Event was required by the project agreement to be covered by insurance.
___________________________________________________________________
57 This principle is currently under review for events which are controlled or better managed by the private party and for which only time relief (and not money) should be given. Separate guidance material will be issued if any change is made to the current principle.