(a) "Modifications" will be defined on a project by project basis but will generally include:
(i) in the design and construction phase, changes to the Design Requirements; and
(ii) in the operating phase, changes to the facility or the Contracted Services,
but will not include:
• minor changes to the facility where 'minor' may be defined with reference to an agreed monetary threshold and/or defined as being works of a non-structural nature which are requested by government and do not result in a delay to Completion, including any Minor Works as outlined in section 19.8;
• the development and refinement of the design documentation in accordance with the project agreement; or
• any other changes to the works, facility or Contracted Services required to ensure the facility is fit for its intended purposes.