7.5.3.  Implications for projects currently under DE&S management

The growth in cost and duration between Initial Gate and ISD has significant implications across the current portfolio of projects. Applying the average duration growth of 81% (see Figure 7-6) and average cost growth of 42% (see Figure 7-7) to the Initial Gate forecasts of the category A-C projects that are currently active74, the overall impact of cost and duration overruns on defence acquisition can be estimated. This analysis is shown in Table 7-7.

 

Assessment phase and Demonstration and Manufacture
phase

 

 

Average duration

Total cost

Initial Gate forecast of current portfolio of category A-C projects in CMIS

67 months

£82.4bn

Average percentage growth from Initial Gate to ISD

81%

42%

Increase that would be observed in current portfolio

55 months

£34.8bn

Source: CMIS, Review team analysis

Table 7-7: Implications on the current EPP of duration and cost growth (indicative)

Table 7-7 indicates that the total expected cost overrun is c.£35bn and the average project is expected to slip by nearly 5 years.




__________________________________________________________________________________________________________________________________
74  As at February 2009