7.7.1. Conceptual framework for the full cost of delay

The Review team is concerned that current Departmental project management and accounting practices fail to capture the true cost of delay both at a Departmental and a system level. To attempt to better understand the cost of delay, the team explored a range of potential impacts, from obvious cost increases measured directly as cost-to-complete escalation, to a range of hidden or unattributed cost increases both inside and outside the EP. Using available information (which is often limited), the analysis attempted to allocate a range of costs around delay impacts, expressed on a per annum basis.

The factors considered are shown in Table 7-9 below, with further detail provided in Appendix G.

 

Sources and analytical estimation techniques used

Unproductive project costs77

Regression analysis of CMIS data

Hidden industry costs

Review of accounts of major suppliers to MoD Interviews with IPT Leaders

Potential capability gap costs

Analysis of UOR spending Interviews with IPT Leaders

Run-on equipment costs

Review of run-on costs identified in NAO Major Project Reports

Generalisation from limited sample to whole EPP based on two different methodologies

MoD internal costs

Analysis of DE&S costs captured in Administrative Cost Regime (mainly payroll costs) Estimated additional management time dedicated to planning round

Table 7-9: Summary of analyses undertaken to understand cost of delay

Whilst best endeavours have been applied in deriving estimates for the total cost of delay at a Departmental level, it should be noted that there is substantial uncertainty surrounding the estimation of these costs at this level arising from the need to generalise from relatively few examples in each case. The summary of estimates presented in Table 7-10 are, therefore, highly indicative.

£m p.a.

Low estimate

High estimate

Unproductive project costs

500

1,200

Hidden industry costs

100

350

Potential capability gap costs

110

250

Run-on equipment costs

100

130

MoD internal costs

110

220

Estimated annual cost of delay

920

2,150

Source: Review team estimates

Table 7-10: Estimates of cost of delay (indicative)

The results appear startling, particularly given that the annual expenditure on the EPP is only around £6bn. Some of the costs, however, appear in cost centres outside the EPP so are effectively hidden costs. Unproductive project costs from delay in the year may also not show up within the year, though they will need to be covered eventually to get the same level of capability. Hence the inputs of £6bn per year will not produce £6bn of productive output as planned, but a level reduced by unproductive cost increases. These impacts are illustrated in Figure 7-13 below. For intended productive input of £6bn in expenditure, the effect post-delay may be a level as low as £4bn that will prove valuable, once unproductive costs across the system are taken into account.

Annual system cost of EPP delays

Source: CMIS (Feb 2009); NAO Major project reports; Review team analysis; DE&S management data; Company annual reports; Press

Figure 7-13: Conceptual system costs of delay




__________________________________________________________________________________________________________________________________
77 It should be noted that whilst some unproductive project costs are incurred in directly overcoming technical issues in developing the capability, others are incurred essentially as a result of Departmental behaviour in managing the portfolio of projects underway