2.40 In 2010-11, there was a total of 72 months slippage in the forecast achievement of FOC for the 22 projects that were also included in the 2009-10 MPR. This represents a three per cent increase in the scheduled timeframe for this group of projects. However, this also includes C-17 Heavy Airlift, which is now forecast to achieve FOC in line with its original schedule.74
2.41 Figure 11 shows that the in-year schedule slippage involved the following projects:
• AWD Ships (delays due to issues experienced with the initial block production and shipyard capacity);
• Hornet Upgrade (the project is waiting on the completion of Operational Test and Evaluation and other work by the Royal Australian Air Force (RAAF));
• C-17 Heavy Airlift (the project is waiting on the RAAF to declare FOC);
• Air to Air Refuel (further work required to the military avionics and boom refuelling system);
• HF Modernisation (delays in gaining scope change approval and available skilled project office personnel); and
• ANZAC ASMD 2B, and ANZAC ASMD 2A (delays linked to the change in the projects' acquisition strategy).
2.42 In contrast, the Armidales project's forecast FOC schedule decreased in-year due to a successful rectification program.
Figure 11
In-year (2010-11) schedule changes to achieving FOC (months increase/ decrease in schedule)
|
|
Source: | 2010-11 MPR. |
Note1: | The ANAO review indicates that 17 of the 25 MPR projects with FOC dates did not record changes to the relevant FOC dates during the year. In the case of new projects included in the 2010-11 MPR, the PDSSs do not require projects to outline their schedule status as 30 June 2010 and so do not enable the ANAO to establish whether in-year schedule changes had occurred in 2010-11. |
__________________________________________________________________________________
74 In the 2009-10 MPR, the C-17 Heavy Airlift project was reported as being forecast to achieve FOC 11 months ahead of schedule. Australian National Audit Office, 2009-10 Major Projects Report, p. 250.