Strengthening Projects of Concern Process

1.58  The vast majority of the DMO's major projects are delivering the materiel element of capability to the ADF as planned. However, a small number of DMO projects and sustainment products require additional senior management attention to address significant risks relating to schedule, cost, materiel capability and/or commercial factors.

1.59  In consultation with the Government, the DMO has developed a focused management regime for troubled projects and sustainment products identified as 'Projects of Concern' (POC). The POC remediation regime involves close engagement with industry, Defence and Government.

1.60  The POC regime is closely linked to both the EI&W framework and the Gate Review process. Projects triggering one or more EI&W thresholds are usually subject to a diagnostic Gate Review Assurance Board before recommendations are presented to Government on the project's status.

1.61  Significant outcomes for POC during 2010-11 included:

•  Conduct of the inaugural POC summits between the Minister for Defence Materiel, Defence and CEOs from industry with contractual responsibility for projects on the POC list. These summits will continue to be held twice yearly.

•  Successful remediation of the JP2043 Phase 3A - High Frequency Modernisation and AIR5333 Vigilare projects, and their subsequent removal from the POC list.

•  Removal of the JP2048 Phase 1A - LPA Watercraft project from the POC list through the Government's decision to cancel the project.

1.62  The list of POC projects at 30 June 2011 is contained in Table 1.3.

Table 1.3 - List of Projects of Concern at 30 June 2011

Project Name

Project Number

Date Added

Airborne Early Warning  & Control Aircraft

AIR 5077 Phase 3

Date Added

January 2008

Field Vehicles and Trailers (Medium Heavy Capability segment only)

LAND 121 Phase 3

July 2008

Air to Air Refuelling

AIR 5402

October 2010

Anzac Ship Anti Ship Missile Defence

SEA 1448 Phase 2B

January 2008

Lightweight Torpedo Replacement

JP 2070

January 2008

Tactical Unmanned Aerial Vehicles

JP 129 Phase 2

September 2008

Electronic Support Measures Upgrade for AP-3C Orion aircraft

AIR 5276 Phase 8B

October 2010

Follow-on Stand Off Weapon

AIR 5418 Phase 1

November 2010

Collins Class Submarine Sustainment

CN10

November 2008