2.1 Project Budget History

Date

Description

Base Date $m

Current $m

Contractor

Notes

2.1 Project Budget History

 

 

 

 

1

Jun 07

Original Approved

7,207.4

7,207.4

Jun 11

Price Indexation

 

1,173.2

Jun 11

Exchange Variation

(448.8)

Jun 11 

Total Budge

7,207.4

7,931.8