| Review | Major System / Platform Variant | Original Planned | Current Planned | Achieved /Forecast | Variance (Months) | Notes | |
| System Integration | Ship 1 Complete Hull Integration | Dec 12 | Dec 12 | Dec 13 | 12 | 1, 3 | |
| Ship 1 Start Combat System Light Off | Dec 13 | Dec 13 | Dec 14 | 12 | 2, 3 | ||
| Ship 2 Complete Hull Integration | Mar 14 | Mar 14 | Mar 15 | 12 | 3 | ||
| Ship 2 Start Combat System Light Off | Mar 15 | Mar 15 | Mar 16 | 12 | 3 | ||
| Ship 3 Complete Hull Integration | Jun 15 | Jun 15 | Jun 16 | 12 | 3 | ||
| Ship 3 Start Combat System Light Off | Jun 16 | Jun 16 | Jun 17 | 12 | 3 | ||
| Acceptance | Ship 1 - Commencement of Category 5 Trials | Aug 14 | Aug 14 | Aug 15 | 12 | 3 | |
| Ship 1 - Provisional Acceptance (Initial Materiel Release) | Dec 14 | Dec 14 | Dec 15 | 12 | 3 | ||
| Ship 2 - Commencement of Category 5 Trials | Nov 15 | Nov 15 | Nov 16 | 12 | 3 | ||
| Ship 2 - Provisional Acceptance (Materiel Release 2) | Mar 16 | Mar 16 | Mar 17 | 12 | 3 | ||
| Ship 3 - Commencement of Category 5 Trials | Feb 17 | Feb 17 | Feb 18 | 12 | 3 | ||
| Ship 3 - Provisional Acceptance (Materiel Release 3) | Jun 17 | Jun 17 | Jun 18 | 12 | 3 | ||
| Notes | |||||||
| 1 | Complete Hull Integration is achieved when the last erection joint is structurally inspected and accepted. | ||||||
| 2 | Start Combat System Light Off verifies the readiness of the first set of installed combat system equipment for CAT 4 testing. | ||||||
| 3 | Difficulties with initial block production and shipyard capacity issues have affected the schedule for the first ship which will be delayed by 12 months. This has a flow on effect for Ships 2 and 3. | ||||||