Project Lesson | Categories of Systemic Lessons |
Formation of the Alliance, a new organisational structure- takes time and effort to develop the culture necessary to achieve improved outcomes. An external facilitator was engaged to assist in the initial and ongoing development of the Alliance and this has proved invaluable. | Governance |
The Program Office, originally located in both Canberra and Adelaide was relocated to Adelaide to improve operations and interactions with the Alliance. The relocation involved considerable effort and a resultant loss in knowledge of staff who did not relocate. Earlier consolidation of the Program Office would have been beneficial. | Resourcing |
The interpretation of the requirements for fitness of purpose of dr5awings is different between contracting parties. A review of all product types prior to contract and interrogation of the delivery schedule to confirm sufficient time for reviews and incorporation of comments is necessary. | Contract Management |
The shipbuilding capacity of shipyards involved in a project like AWD needs to be assessed in detail in terms of precise capacity to undertake production engineering as well as the workload constraints of facilities, production supervision and overall workforce numbers taking into consideration the total contracts conducted at the shipyard in parallel. | Resourcing First of Type Equipment |
The schedule that plans the transition from design to production needs detailed evaluation by the designer(s) and the production shipyard(s) to ensure the balance between commencing production and completing very detailed design is appropriately balanced and agreed. | Scheduling |