Project Data Summary Sheet196
| Project Name | AIRBORNE EARLY WARNING AND CONTROL AIRCRAFT |
|
| Project Number | AIR 5077 Phase 3 | |
| Capability Type | New | |
| Service | Royal Australian Air Force | |
| Government 1st Pass Approval | Dec 97 | |
| Government 2nd Pass Approval | Dec 00 | |
| Total Approved Budget (Current) | $3,859.5m | |
| 2010-11 Budget | $217.1m | |
| Project Stage | System Integration and Test | |
| Complexity | ACAT I |
__________________________________________________________________________________________
196 Notice to reader
| Future dates, Sections; 1.3 (Major Challenges), 4.1 (Measures of Materiel Capability Performance), 5.1 (Major Project Risks) and 5.2 (Major Project Issues) are out of scope for the ANAO's review of this Project Data Summary Sheet. Information on the scope of the review is provided in the Auditor-General's Independent Review Report at p.175. |