Date | Description | Base Date $m | Current $m | Contractor | Notes | |
2.1 Project Budget History |
|
|
|
|
| |
Dec 97 | Original Approved | 2,170.4 |
| 2,170.4 |
| 1 |
|
|
|
|
|
|
|
Jul 98 | Real Variation - | (170.4) | (170.4) |
|
| 2 |
Nov 99 | Real Variation - | 807.9 | 807.9 |
|
| 3 |
Apr 01 | Real Variation - | (166.0) | (166.0) |
|
| 4 |
Mar 02 | Real Variation - | (3.9) | (3.9) |
|
| 5 |
Jun 04 | Real Variation - Scope | 225.6 | 225.6 |
|
| 6 |
Aug 04 | Real Variation - | (2.4) | (2.4) |
|
| 9 |
Aug 04 | Real Variation - | (14.0) | (14.0) |
|
| 8 |
Jun 05 | Real Variation - | (1.0) | (1.0) |
|
| 8 |
Aug 05 | Real Variation - | (4.8) | (4.8) |
|
| 9 |
|
| 671.0 |
| 671.0 |
|
|
Jun 11 | Price Indexation |
|
| 1,111.1 |
| 10 |
Jun 11 | Exchange |
|
| (92.9) |
|
|
Jun 11 | Total Budget | 2,841.4 |
| 3,859.5 |
|
|
|
|
|
|
|
|
|