3.1 Design Review Progress

Review

Major System / Platform Variant

Original Planned

Current Planned

Achieved /Forecast

Variance (Months)

Notes

Preliminary
Design

Airborne Mission System

Jul 02

Jun 02

(1)

1

Operational Mission Simulator

Jan 03

Apr 03

3

Mission Support System

Mar 03

Apr 03

1

Operational Flight Trainer

Aug 03

Jul 03

(1)

Airborne Early Warning and Control Support Facility

Nov 03

Oct 03

(1)

Critical
Design

Airborne Mission System

Feb 03

Dec 02

(2)

Operational Mission Simulator

Nov 03

Nov 03

0

Mission Support System

Dec03

Nov 03

(1)

Operational Flight Trainer

May 04

Apr 04

(1)

Airborne Early Warning and Control Support Facility

Oct 04

Sep 04

(1)

Notes

1

Variances to Design Review were due to various minor causes.