| Test and | Major System / Platform Variant | Original Planned | Current Planned | Achieved | Variance (Months) | Notes |
| System | Airborne Mission System | Mar 06 | Sep 11 | May 12 | 74 | 2 |
| Operational Mission Simulator | Mar 06 | Dec 10 | Nov 10 | 57 |
| |
| Operational Flight Trainer | Dec 05 | Dec 05 | Dec 05 | 0 |
| |
| Mission Support System | Jul 06 | Oct 08 | Aug 11 | 61 | 3 | |
| AEW&C Support Facility | Dec 06 | Dec 10 | Nov 11 | 61 | 4 | |
| Acceptance | Airborne Mission System | Nov 06 | Sep 11 | May 12 | 66 | 5 |
| Operational Mission Simulator | May 06 | Sep 11 | Dec 11 | 64 | 4, 5 | |
| Operational Flight Trainer | Mar 06 | Nov 08 | Feb 09 | 35 | 6 | |
| Mission Support System | Aug 06 | Jul 11 | Aug 11 | 60 | 4, 5 | |
| AEW&C Support Facility | Mar 07 | Mar 11 | Nov 11 | 56 | 4, 5 | |
| Notes | ||||||
| 1 | The Current Planned dates reflect the revised schedule agreed as part of the April 2011 commercial settlement, whereas the Forecast dates and associated Variances reflect Defence's assessment of when completion is likely to be achieved. The above dates reflect the completion of testing relating to the Contract Specification and do not include testing associated with the additional compensatory work agreed under the commercial settlement. | |||||
| 2 | Airborne Mission System (AMS) integration continues to challenge progress of the AMS development and test program. Most significant challenges relate to finalisation and integration of the mission computing, datalinks, and electronic support measures subsystems, including integrated maturity, loading and latency, and stability. Supplier hardware availability continues to present challenges to the type and production program. | |||||
| 3 | System Integration Test and Evaluation, previously reported as completed in May 2009, has been resumed as a result of deficiencies subsequently revealed during integrated mission testing. | |||||
| 4 | Ground Support Segments (GSS) continue to be impacted by AMS schedule delays. | |||||
| 5 | Problems associated with sub-system integration; mission computing, loading and latency, radar and electronic support measures maturity and stability; and supplier hardware availability. | |||||
| 6 | Disagreement between Boeing and Commonwealth over specification requirements. | |||||