Maturity Score | Attributes | Total | ||||||||
Schedule | Cost | Requirement | Technical Understanding | Technical | Commercial | Operations and Support | ||||
Project Stage | Benchmark | 8 | 7 | 8 | 8 | 8 | 8 | 8 | 55 | |
System Integration and Test | Project Status | 7 | 7 | 8 | 8 | 8 | 6 | 9 | 53 | |
| • Schedule: Delays associated with sub-system integration; mission computing, loading and latency, radar and electronic support measures maturity and stability; and supplier hardware availability • Commercial: The Commonwealth assesses that there is some continuing risk to Boeing's delivery plans. • Operations and Support: Operations and support systems have begun transitioning to the operational environment with Initial Acceptance of the first four aircraft. | |||||||||
| ||||||||||