Test and Evaluation | Major System / Platform Variant | Original Planned | Current | Achieved /Forecast | Variance | Notes | |
System | MRH aircraft - Phase 2 | Jul 06 | Nov 06 | Dec 06 | 5 |
| |
MRH aircraft - Phase 4/6 | N/A | N/A |
| N/A |
| ||
MRH Software Support Centre | N/A | Oct 08 | Nov 08 | 1 |
| ||
Electronic Warfare Self | N/A | N/A | Nov 07 | N/A |
| ||
Ground based Mission planning and Management System | N/A | N/A |
| N/A |
| ||
MRH Instrumented System | Nov 08 | May 09 | Dec 09 | 13 | 1 | ||
Full Flight and Mission Simulators | Jun 11 | Sept 11 | Sep 11 | 4 | 2 | ||
Acceptance | Type Acceptance Review | Oct 07 |
| Dec 07 | 2 | 3 | |
Type Acceptance Review Special Flight Permit 2 | Jun 08 |
| Jun 08 | 0 |
| ||
Extension Special Flight Permit 2 | Feb 09 |
| Feb 09 | 0 |
| ||
Australian Military Type Certificate | Dec 08 | Dec 10 | Dec 11 | 36 | 4 | ||
Full Flight and Mission Simulators | Mar 13 | Mar 13 | Mar 13 | 0 | 5 | ||
Ground based Mission planning and Management System Lot 1 | Feb 09 | Sep 09 | Dec 09 | 10 |
| ||
Ground Mission planning and Management System Lot 2 | Feb 09 | Dec 09 | Apr 10 | 14 |
| ||
MRH Software Support Centre | Feb 09 | Feb 09 | Dec 08 | (2) |
| ||
Electronic Warfare Self Protection Support System | Dec 07 | Dec 07 | Dec 07 | 0 |
| ||
MRH Instrumented System | Mar 10 | Jun 10 | Jul 11 | 16 |
| ||
Aircraft | MRH aircraft #01 (First aircraft) | Dec 07 |
| Dec 07 | 0 |
| |
MRH aircraft #05 (First Australian built aircraft) | Dec 08 |
| Dec 08 | 0 |
| ||
MRH aircraft #13 (Most recent) | Mar 10 | Sep 10 | Sep 10 | 6 |
| ||
MRH aircraft #14 (Next aircraft) | Jul 10 | Jul 11 | Jul 11 | 12 | 6 | ||
MRH aircraft #46 (Final aircraft) | Jul 14 | Jul 14 | Jul 14 | 0 |
| ||
Notes | |||||||
1 | The 13 month delay to closure of Test Readiness Review was due to electronic compatibility test design issues not resolved until November 2009. This delay was mitigated by the development of an interim MRH Instrumentation System capability used for a test activity in October 2009. | ||||||
2 | Delays experienced through the FFMS design phase have flowed into development and production activities. Some schedule recovery has occurred as the Contractor has adopted parallel development of FFMS#1 and FFMS#2. | ||||||
3 | The first Airworthiness Board (for a Special Flight Permit) was conducted in November 2007 and granted in December 2007. | ||||||
4 | Achievement of the Australian Military Type Certificate has proved problematic due to insufficient levels of Rate of Effort. Rate of Effort is required to validate that in-service support arrangements for the fleet are sufficient to cope with current numbers of aircraft and are growing in maturity to meet fleet requirements. Further, the numbers of trained aircrew have been limited by the low Rate of Effort and are a criterion for Australian Military Type Certificate. Operating under the Special Flight Permit rather than an Australian Military Type Certificate has not caused any project delay to date. | ||||||
5 | FFMS schedule compression has occurred due to the adoption of a parallel integration and testing program for both simulators. The testing program is ambitious and the likelihood for success can be better gauged once testing commences in the second half of 2011. | ||||||
6 | Acceptance of aircraft ceased on 22 November 2010 due to Contractual non conformity. Resumption of aircraft acceptance will commence when the Contractor demonstrates the capability in accordance with the contract. | ||||||