Item |
| Original Planned | Achieved /Forecast | Variance (Months) | Variance Explanation / Implications |
Initial Materiel Release (IMR) | Army / Navy | Jan 12 | Jan 12 | 0 |
|
Navy | Jul 10 | Dec 11 | 17 | A delay to IOC - Navy is due to the low achieved Rate of Effort and its effect on aircrew training. | |
Army | Apr 11 | Oct 12 | 18 | A delay to IOC - Army is due to the low achieved Rate of Effort and its effect on aircrew training. | |
Final Materiel Release (FMR) | Army / Navy | Oct 14 | Oct 14 | 0 |
|
Final Operational | Navy | Dec 12 | Dec 12 | 0 | N/A |
Army | Jul 14 | Jul 14 | 0 | N/A |
Schedule Status as at 30 Jun 11
|