3.3 Progress Towards Materiel Release and Operational Capability Milestones

Item

 

Original Planned

Achieved /Forecast

Variance (Months)

Variance Explanation / Implications

Initial Materiel Release (IMR)

Army / Navy

Jan 12

Jan 12

0

 

Initial Operational Capability (IOC)

Navy

Jul 10

Dec 11

17

A delay to IOC - Navy is due to the low achieved Rate of Effort and its effect on aircrew training.

Army

Apr 11

Oct 12

18

A delay to IOC - Army is due to the low achieved Rate of Effort and its effect on aircrew training.

Final Materiel Release (FMR)

Army / Navy

Oct 14

Oct 14

0

 

Final Operational

Navy

Dec 12

Dec 12

0

N/A

Capability (FOC)

Army

Jul 14

Jul 14

0

N/A

Schedule Status as at 30 Jun 11