Description | Remedial Action |
The schedule to achieve an Australian Military Type Certificate and Service Release in 2011 will be adversely affected due to the inability to generate the required aircraft rate of effort. | Resolve technical and spares issues that restrict aircraft availability. Streamline Commonwealth and Industry support processes to maximise available flight opportunities. |
The schedule to achieve an Australian Military Type Certificate and Service Release in 2010 will be adversely affected by failing to achieve a sufficiently mature MRH System. | Measure progress against capability Key Performance Indicators. Maximise opportunities to use certification processes of other NH90 nations. Maintain focus on achieving capability milestones and targets. |
The technical and flight operational airworthiness will be affected by the immaturity of the MRH90 flight manual for Service Release leading to an impact on schedule, performance and supportability. | The project and Australian Aerospace are developing an Australianised Aircrew Information Set. |