Test and Evaluation | Major System / Platform Variant | Original Planned | Current Planned | Achieved | Variance (Months) | Notes | ||
System Integration | Phase 1 | Instrument Landing System Antennae Qualification | Jul 08 |
| May 09 | 10 | 1 | |
Instrument Landing System - Aircraft Integration Test | Jan 09 - |
| May 09 - | 3 | 2 | |||
Aircraft Software Integration | Mar 09 - |
| Mar 09 - | 5 | 3 | |||
Electronic Warfare | Mar 09 |
| May 10 | 14 | 4 | |||
Automated | Aug 09 |
| Aug 09 | 0 |
| |||
Phase 2 | N/A | N/A | N/A | N/A | 5 | |||
Acceptance | Phase 1 | Lot 32 Aircraft | Jul 09 - |
| Jul 09 - | 0 |
| |
Lot 33 Aircraft | Aug 10 - |
| Aug 10 - | 0 |
| |||
Aircraft Post-Production Test and Evaluation (US Navy) | Jul 09 - |
| Jul 09 - | 14 | 6 | |||
Electronic Warfare | May 09 |
| Jun 10 | 13 | 7 | |||
Automated | Aug 09 |
| Aug 09 | 0 |
| |||
Tactical Operation | Mar 10 |
| May 10 | 2 | 8 | |||
Low Cost Trainers | Feb 10 |
| May 10 | 3 | 9 | |||
Visual Environment | Sept 09 |
| Oct 09 | 1 | 10 | |||
Computer Based | Nov 09 |
| Dec 09 | 1 |
| |||
Phase 2 | Mar 10 |
| Mar 10 | 0 |
| |||
N/A |
| Feb 10 | 0 | 11 | ||||
Mar 10 | Jun 13 | Jun13 | 39 | 12 &13 | ||||
AMRAAM C-7 | Dec 11 | Jun 14 | Jun 14 | 30 | 14 | |||
Notes | ||||||||
1 | Instrument Landing System antennae qualification and integration tests delayed due to a test failures of the antennas and the need to redesign. | |||||||
2 | Airframe Integration Test - Slip due to failure of Instrument Landing System antennae. | |||||||
3 | Software Integration - classified. | |||||||
4 | The Electronic Warfare data library testing was delayed due to the US Navy adopting a new design process, and the continuing issue of classified data being unable to be released. | |||||||
5 | Integration of weapons onto aircraft is within the scope for AIR 5349 Phase 1. | |||||||
6 | Post-production test and evaluation affected by the delays in the instrumented landing system qualification and aircraft software integration. The fourteen month delay related to the first aircraft which remained in the US under US Navy custody for Contractor rectification testing with the avionics issue and US Navy weapon risk mitigation activity. | |||||||
7 | Thirteen month delay due to System Integration failures and delays with USN development. | |||||||
8 | Two month variance due to delays in the US Government data release approval process and approval required for US export of equipment. | |||||||
9 | Three month delay due to late delivery of Low Cost Trainer facility at Amberley. | |||||||
10 | One month variance due to delays in the US Government data release approval process and approval required for US export of equipment. | |||||||
11 | Due to JSOW C-1 slippage, JSOW. C was acquired to meet December 2010 IOC requirement. | |||||||
12 | Deliveries of post FOC weapons are a result of the spiral acquisition process. This is inherent in a modern weapons project whereby new weapons will be procured following discontinued production runs of the JSOW-C and AMRAAM C-5 weapons variant. | |||||||
13 | Reflects up to 39 months delay in US program of JSOW C-1, noting original planned date was based on US Navy advice prior to full disclosure of US Navy development schedule. JSOW C missiles were purchased to provide required IOC/FOC capability of JSOW C-1. Since acquisition of JSOW C meets the IOC/FOC requirement of JSOW C-1 (March 2010), actual delay should be considered as post FOC, December 2012 (6 months). | |||||||
14 | Reflects variance of 30 months due to earliest availability of AMRAAM C-7 from US Government. | |||||||