3.3 Progress Toward Materiel Release and Operational Capability Milestones

Item

Original 
Planned

Achieved /Forecast

Variance (Months)

Variance Explanation / Implications

Initial Materiel Release (IMR)

Phase 1

N/A

Mar 10

 

 

Phase 2

N/A

Dec 10

 

 

Initial Operational Capability (IOC)

Phase 1

Dec 10

Dec 10

0

 

Phase 2

Dec 10

Dec 10

0

 

Final Materiel Release (FMR)

Phase 1

Oct 11

Oct 11

0

 

Phase 2

Aug 12

Aug 12

0

 

Final Operational Capability (FOC)

Phase 1

Dec 12

Dec 12

0

 

Phase 2

Dec 12

Dec 12

0

 

Schedule Status as at 30 Jun 11