4.1 Measures of Materiel Capability Performance Phase 2 (Weapons)

Pie Chart: Percentage Breakdown of Materiel Capability Performance

Green:

The Project is currently meeting capability requirements as expressed in the suite of Capability Definition Documentation and in accordance with the requirements of the relevant Technical Regulatory Authorities

Amber: 

The Project Office has been advised by RAAF that some deliverables are a low Service priority, thereby acknowledging that original agreed milestones cannot be achieved. Formal changes to the milestone agreement have been completed. Project's not yet been completed

Red: 
N/A