2.1 Project Budget History

Date

Description

Base
Date $m

Current $m

 

Contractor

Notes

2.1 Project Budget History

 

 

 

 

 

Aug 07

Original Approved 

2,745.3

 

2,745.3

 

 

 

 

 

 

 

 

 

Jan 09

Real Variation - 
Scope

(14.8)

(14.8)

 

 

1

Jan 09

Real Variation -
Transfer

4.5

4.5

 

 

2

Jun 11

Price Indexation

(10.3)

 

(10.3)

 

 

 

 

 

 

746.8

 

 

Jun 11

Exchange Variation

 

 

(217.9)

 

3

Jun 11

Total Budget

2,735.0

 

3,263.9