Test and Evaluation | Major System / Platform Variant | Original Planned | Current Planned | Achieved /Forecast | Variance (Months) | Notes | |
Test | LLC: Trucks (Lightweight Carryall Station Wagen, Lightweight Carryall Soft Top, Light Dual Cab, Light Cab Chassis) | Oct 09 |
| Dec 09 | 2 | 1 | |
LLC: Truck, Light, Surveillance and Reconnaissance vehicle only | Aug 10 |
| Dec 11 | 16 | 1 | ||
LLC: Truck, Lightweight, Carryall hard Top | Oct 09 |
| Oct 10 | 12 | 1 | ||
LLC: Modules (Cargo Cab Chassis, Canine Dual Cab) | Jan 10 |
| May 10 | 4 | 1 | ||
LLC: Module (Light Ambulance, Cab Chassis) | Oct 10 | Jan 12 | Jan 12 | 15 | 1 | ||
LLC: Modules (Command Post, Mobile Dual Cab; Command Post, Cab Chassis) | Jan 10 | May 11 | May 11 | 16 | 1 | ||
LLC: Module (Light PCRS Cab Chassis) | Oct 10 | Nov 11 | Nov 11 | 13 | 1 | ||
LLC: Tray (Light Surveillance and Reconnaissance) | Aug 10 | Dec 11 | Dec 11 | 16 | 1 | ||
LLC: Light & Lightweight Trailers | Jul 11 |
| Jul 11 | 0 |
| ||
Functional | LLC: Trucks (Lightweight Carryall Station Wagon, Lightweight Carryall Soft Top, Light Dual Cab, Light Cab Chassis) | Aug 10 |
| Aug 10 | 0 |
| |
LLC: Truck, Light, Surveillance and Reconnaissance vehicle only | Feb 11 |
| Nov 10 | 3 | 1 | ||
LLC: Truck, Lightweight, Carryall hard Top | Aug 10 |
| Oct 10 | 2 | 1 | ||
LLC: Modules (Cargo Cab Chassis, Canine Dual Cab) | Jun 10 |
| Nov 10 | 5 | 1 | ||
LLC: Module (Light Ambulance, Cab Chassis) | Apr 11 | Apr 12 | Apr 12 | 12 | 1 | ||
LLC: Modules (Command Post, Mobile Dual Cab; Command Post, Cab Chassis) | Aug 10 | Oct 11 | Oct 11 | 14 | 1 | ||
LLC: Module (Light PCRS Cab Chassis) | Apr 11 | Mar 12 | Mar 12 | 11 | 1 | ||
LLC: Tray (Light Surveillance and Reconnaissance) | Feb 11 | Mar 12 | Mar 12 | 13 | 1 | ||
Acceptance Verification and Validation | LLC: Light & Lightweight Trailers | Jul-Oct |
| Jul-Oct 11 | 0 |
| |
Notes | |||||||
1 | LLC Reviews with a variance between the originally planned and achieved/forecast dates is due to changes in specification by the Commonwealth. | ||||||