3.2 Contractor Test and Evaluation Progress

Test and Evaluation

Major System / Platform Variant

Original Planned

Current Planned

Achieved /Forecast

Variance (Months)

Notes

Test
Readiness
Review

LLC: Trucks (Lightweight Carryall Station Wagen, Lightweight Carryall Soft Top, Light Dual Cab, Light Cab Chassis)

Oct 09

 

Dec 09

2

1

LLC: Truck, Light, Surveillance and Reconnaissance vehicle only

Aug 10

 

Dec 11

16

1

LLC: Truck, Lightweight, Carryall hard Top

Oct 09

 

Oct 10

12

1

LLC: Modules (Cargo Cab Chassis, Canine Dual Cab)

Jan 10

 

May 10

4

1

LLC: Module (Light Ambulance, Cab Chassis)

Oct 10

Jan 12

Jan 12

15

1

LLC: Modules (Command Post, Mobile Dual Cab; Command Post, Cab Chassis)

Jan 10

May 11

May 11

16

1

LLC: Module (Light PCRS Cab Chassis)

Oct 10

Nov 11

Nov 11

13

1

LLC: Tray (Light Surveillance and Reconnaissance)

Aug 10

Dec 11

Dec 11

16

1

LLC: Light & Lightweight Trailers

Jul 11

 

Jul 11

0

 

Functional
Configuration
Audit

LLC: Trucks (Lightweight Carryall Station Wagon, Lightweight Carryall  Soft Top, Light Dual Cab, Light Cab Chassis)

Aug 10

 

Aug 10

0

 

LLC: Truck, Light, Surveillance and Reconnaissance vehicle only

Feb 11

 

Nov 10

3

1

LLC: Truck, Lightweight, Carryall hard Top

Aug 10

 

Oct 10

2

1

LLC: Modules (Cargo Cab Chassis, Canine Dual Cab)

Jun 10

 

Nov 10

5

1

LLC: Module (Light Ambulance, Cab Chassis)

Apr 11

Apr 12

Apr 12

12

1

LLC: Modules (Command Post, Mobile Dual Cab; Command Post, Cab Chassis)

Aug 10

Oct 11

Oct 11

14

1

LLC: Module (Light PCRS Cab Chassis)

Apr 11

Mar 12

Mar 12

11

1

LLC: Tray (Light Surveillance and Reconnaissance)

Feb 11

Mar 12

Mar 12

13

1

Acceptance Verification and Validation

LLC: Light & Lightweight Trailers

Jul-Oct 
11

 

Jul-Oct 11

0

 

Notes

1

LLC Reviews with a variance between the originally planned and achieved/forecast dates is due to changes in specification by the Commonwealth.