5.2 Major Project Issues 

Description

Remedial Action

MHC: Initial Operational Capability (IOC) has been affected by the MHC resubmission activity, leading to an impact on schedule.

The remedial action is to hasten evaluation and negotiation activities, to reduce the impact on schedule.

The remedial action is cognisant of the associated risk of having multiple tenderers to undertake negotiations which will further extend the introduction into service schedule.

MHC: Army's Basis of Provisioning is unaffordable.

The remedial action is to seek Military off the Shelf platforms and limit modification to critical ADF requirements and those necessary for legislative compliance.