6.1 Project Maturity Score and Benchmark

Maturity Score

Attributes

Total

Schedule

Cost

Requirement

Technical Understanding

Technical Difficulty

Commercial

Operations Support

Project Stage

Benchmark

5

5

5

5

5

5

5

35

Second Pass

Project Status

4

4

5

7

6

5

4

35

Explanation

Schedule, Cost, Operation and Support: the difference is a result of Land 121 being a multi segmented project with each segment currently at different stages of the project.

LLC: vehicles and trailers are in contract.

MHC: vehicles and trailers are not yet in negotiation or contract. MHC planned contract signature date is subject to the down - selection outcome which is anticipated to be announced in late 2011. MHC is still subject to a revised Second Pass.

Technical Understanding and Technical Difficulty: The reason for the difference is that there is a better understanding of the technical requirements across all segments of the project even though they are at different stages.

2009-10 DMO MPR Status- - - -

2010-11 DMO MPR Status- - - -