2.1  Project Budget History

Date

Description

Base Date $m

Current $m

Contractor

Notes

2.1 Project Budget History

 

 

 

 

 

Nov 03

Original Approved

3.1

 

3.1

 

1

Sep 04

Real Variation - Scope

4.8

4.8

 

 

2, 3

Nov 05

Real Variation - Scope

29.6

29.6

 

 

4

Jun 07

Government Second Pass Approval

2,920.8

2,920.8

 

 

 

Oct 08

Real Variation - Transfer

9.3

9.3

 

 

5

 

 

2,967.6

 

2,967.6

 

 

Jun 11

Price Indexation

 

 

428.4

 

6

Jun 10

Exchange Variation

 

 

(273.4)

 

 

Jun 10

Total Budget

2,967.6

 

3,122.6