3.2  Contractor Test and Evaluation Progress

Review

Major System / Platform Variant

Original Planned

Current Planned

Achieved /Forecast

Variance (Months)

Notes

System Integration

LHD Ships 1 and 2

Mar 15

Mar 15

Mar 15

0

 

Acceptance

LHD Ship 1 Project Acceptance

Jan 14

Jan 14

Feb 14

1

1

LHD Ship 2 Project Acceptance

Aug 15

Aug 15

Aug 15

0

 

LHD Final Acceptance

Sep 15

Sep 15

Sep 15

0

 

Notes

1

Due to latest revised dates for heavy lift ship as advised by Navantia