Item | Original Planned | Achieved /Forecast | Variance (Months) | Variance Explanation / Implications |
Initial Materiel Release (IMR) | ||||
Jan 14 | Feb 14 | 1 | Revised forecast date based on an approved contract change. | |
Aug 15 | Aug 15 | 0 | N/A | |
Jun 15 | Dec 14 | (6) | As per approved MAA. | |
Nov 16 | Nov 16 | 0 | N/A | |
Final Materiel Release (FMR) | Aug 15 | Aug 15 | 0 | N/A |
Nov 16 | Nov 16 | 0 | As per approved MAA. | |
Schedule Status as at 30 Jun 11