Maturity Score | Attributes |
| ||||||||
Schedule | Cost | Requirement | Technical Understanding | Technical Difficulty | Commercial | Operations and Support | Total | |||
Project Stage | Benchmark | 7 | 7 | 7 | 8 | 7 | 7 | 7 | 50 | |
Critical Design Review | Project Status | 8 | 7 | 7 | 7 | 7 | 8 | 6 | 50 | |
Explanation | • Schedule: critical path activities are well advanced and detailed planning for remaining activities is sound. Variance trends provide confidence that schedule will be within the tolerance of the Materiel Acquisition Agreement. • Technical Understanding: Needs are understood. Arrangements to operate and support the capability are being arranged. • Commercial: Contractor is performing and delivering as contracted. • Operations and Support: Procurement of training and spares yet to be contracted. | |||||||||
| ||||||||||