6.1  Project Maturity Score and Benchmark

Maturity Score

Attributes

 

Schedule

Cost

Requirement

Technical Understanding

Technical Difficulty

Commercial

Operations and Support

Total

Project Stage

Benchmark

7

7

7

8

7

7

7

50

Critical Design Review

Project Status

8

7

7

7

7

8

6

50

Explanation

•  Schedule: critical path activities are well advanced and detailed planning for remaining activities is sound. Variance trends provide confidence that schedule will be within the tolerance of the Materiel Acquisition Agreement.

•  Technical Understanding: Needs are understood. Arrangements to operate and support the capability are being arranged.

•  Commercial: Contractor is performing and delivering as contracted.

•  Operations and Support: Procurement of training and spares yet to be contracted.

2009-10 DMO MPR Status - - - -

2010-11 DMO MPR Status - - - -