Review | Major System / Platform Variant | Original Planned | Current Planned | Achieved /Forecast | Variance (Months) | Notes | |
Preliminary Design | Mar 03 |
| July 03 | 4 | 1 | ||
Critical Design | Apr 04 | Feb 06 | Feb 06 | 22 | 2 | ||
Notes | |||||||
1 | Aircraft weight was the major issue that delayed the closure of the Preliminary Design Review (PDR) by approximately three months. | ||||||
2 | Design refinements following PDR failed to achieve the weight savings initially expected and considerable additional design effort was required. The original planned CTOL Critical Design Review (CDR), planned for April 04, was re-scheduled to February 2006 after the redesign effort was complete and included the 'roll up' of many lower-tiered reviews. | ||||||