Item | Original Planned | Achieved/Forecast | Variance (Months) | Variance Explanation / Implications |
Materiel Release #1 (MR1) | Sep 17 | Jan 18 | 3 | MR1 is an interim materiel release established for Phase 2A/B Stage 1. |
Initial Materiel Release (IMR) | N/A | N/A | N/A | Achievement of IMR and subsequent Materiel Release and Capability Milestones (IOC/FOC) is dependent on Phase 2A/B Stage 2 approval in 2012. |
N/A | N/A | N/A | Achievement of IMR and subsequent Materiel Release and Capability Milestones (IOC/FOC) is dependent on Phase 2A/B Stage 2 approval in 2012. | |
Final Materiel Release (FMR) | N/A | N/A | N/A | Achievement of IMR and subsequent Materiel Release and Capability Milestones (IOC/FOC) is dependent on Phase 2A/B Stage 2 approval in 2012. |
N/A | N/A | N/A | Achievement of IMR and subsequent Materiel Release and Capability Milestones (IOC/FOC) is dependent on Phase 2A/B Stage 2 approval in 2012. |
Schedule Status as at 30 Jun 11