3.3  Progress Towards Materiel Release and Operational Capability Milestones

Item

Original Planned

Achieved/Forecast

Variance (Months)

Variance Explanation / Implications

Materiel Release #1 (MR1)

Sep 17

Jan 18

3

MR1 is an interim materiel release established for Phase 2A/B Stage 1.

Initial Materiel Release (IMR)

N/A

N/A

N/A

Achievement of IMR and subsequent Materiel Release and Capability Milestones (IOC/FOC) is dependent on Phase 2A/B Stage 2 approval in 2012.

Initial Operational Capability (IOC)

N/A

N/A

N/A

Achievement of IMR and subsequent Materiel Release and Capability Milestones (IOC/FOC) is dependent on Phase 2A/B Stage 2 approval in 2012.

Final Materiel Release (FMR)

N/A

N/A

N/A

Achievement of IMR and subsequent Materiel Release and Capability Milestones (IOC/FOC) is dependent on Phase 2A/B Stage 2 approval in 2012.

Final Operational Capability (FOC)

N/A

N/A

N/A

Achievement of IMR and subsequent Materiel Release and Capability Milestones (IOC/FOC) is dependent on Phase 2A/B Stage 2 approval in 2012.

Schedule Status as at 30 Jun 11