4.1  Measures of Materiel Capability Performance

Pie Chart: Percentage Breakdown of Materiel Capability Performance

Green:
The project is currently on track to deliver the materiel elements as detailed in the approved AIR6000 PH2/AB Materiel Acquisition Agreement.

Amber:
The establishment and implementation of the NACC Australian Industry Support Program is experiencing delays in line with those being experienced by the US Program. Until the US JSF Integrated Baseline Review is finalised and the Australian support program implemented it is uncertain whether the aspirational targets for Australian Industry participation in the JSF Global Program can be reached.

Red:
N/A