Review | Major System / Platform Variant | Original Planned | Current Planned | Achieved /Forecast | Variance (Months) | Notes | |
System Requirements | ARH System | Mar 02 |
| Feb 03 | 11 |
| |
Aircrew Training Devices | Jun 02 |
| Feb 03 | 8 |
| ||
System Design | ARH System | Jun 02 |
| Feb 03 | 8 | 1 | |
ARH System - Delta System Design Review | Mar 03 |
| Apr 03 | 1 |
| ||
Aircrew Training Devices | Apr 03 |
| Jul 03 | 3 |
| ||
Preliminary Design | ARH Tiger | Oct 02 |
| May 03 | 7 | 2 | |
Aircrew Training Devices | Mar 03 |
| Oct 04 | 19 |
| ||
Critical Design | ARH Tiger | Mar 03 |
| Jul 04 | 16 | 3 | |
Aircrew Training Devices | Sep 03 |
| Jun 05 | 21 | 4 | ||
Notes | |||||||
1 | Reliance on the certification of the French Tiger variant was critical to the Australian design review and acceptance program. The DMO's ability to leverage from the French program was adversely impacted because the French program had not achieved design approval outcomes in the timeframe expected. | ||||||
2 | As the ARH is a variant of the French and German Tiger helicopters, the ADF Technical Airworthiness Authority planned to utilise the existing certification work undertaken by the French acquisition agency (Direction Générale de l'Armement). | ||||||
3 | The maturity of the ARH design has required ongoing engineering changes to the approved ARH product baseline presented to the Airworthiness Board at the In Service Date. As a result, subsequent flight testing is required to confirm contract compliance and operational acceptance of incorporated design changes to enable removal of Australian Military Type Certificate and Service Release limitations. | ||||||
4 | The Full Flight and Mission Simulator required customisation to both the visual system and the motion systems following contract signature in order to account for capability deficiencies associated with the proposed simulator design. A major cause of the delay in delivering training devices can be attributed to the efficacy with which the software provided from the aircraft manufacturer's test program is being managed to produce a high fidelity simulator. | ||||||