3.2  Contractor Test and Evaluation Progress

Test and Evaluation

Major System / Platform Variant

Original Planned

Current Planned

Achieved /Forecast

Variance (Months)

Notes

System Integration

Full Flight and Mission Simulator Contractor In-plant

Jul 04

 

Oct 07

39

 

Cockpit Procedures Trainer Oakey Contractor In-plant and On-Site

Jul 04

 

Jun 08

47

 

Cockpit Procedures Trainer Darwin Contractor In-plant and Army In-plant

Jul 04

 

Dec 08

53

 

Acceptance

ARH

Type Acceptance Review Special Flight Permit

Oct 04

 

Jun 05

8

 

Australian Military Type Certificate

Jun 05

 

Oct 05

4

 

Aircrew Training Devices - Final Acceptance Test and Evaluation

Full Flight and Mission Simulator (Transition Training capability)

Feb 05

 

Nov 07

33

 

Full Flight and Mission Simulator (Full Training capability)

Feb 05

 

Nov 09

57

 

Cockpit Procedures Trainer Oakey

Feb 05

 

Nov 09

57

 

Cockpit Procedures Trainer Darwin

Feb 05

 

Feb 10

60

 

Acceptance

ARH #11

Jul 06

 

Apr 08

21

 

ARH #22

Apr 08

Dec 10

Sep 11

43

1

Notes

1

The acceptance of the 22nd production ARH is contracted for July 2011. Achievement of this milestone is now at risk following Australian Aerospace's advice that it would not be able to deliver all 22 ARH by this date. The June 2011 Integrated Master Schedule shows a Forecast Date (Early Finish Date) for the final production aircraft (ARH #22) of September 2011.

Note: Production aircraft (#22) is the 22nd aircraft accepted by the Commonwealth which is not to be confused with the milestone for the 22nd aircraft accepted in the Initial Operational Test and Evaluation configuration under the Acquisition Contract. Australian Aerospace is currently forecasting an Early Finish Date of December 2011 for the 22nd aircraft accepted in the Initial Operational Test and Evaluation configuration milestone (ARH00from retrofit).