Item | Original Planned | Achieved /Forecast | Variance (Months) | Variance Explanation / Implications |
Initial Materiel Release (IMR) | N/A | Sep 09 | N/A |
|
Jun 07 | Apr 10 | 34 | Operational Capability 1 (OC1) (IOC) was granted by Chief of Army on 8 April 2010. | |
Final Materiel Release (FMR) | Jul 12 | Jul 12 | 0 | No FMR originally identified. Current FMR is the date agreed in Amendment No. 2 to the Project Air 87 Phase 2 Materiel Acquisition Agreement. |
Jun 09 | Dec 12 | 42 | The revised FOC date of December 2012 was agreed during the development and subsequent approval of Amendment No. 1 to the Air 87 Phase 2 Materiel Acquisition Agreement in August 2009 and has not changed in Amendment No. 2. |
Schedule Status as at 30 Jun 11
|