4.1  Measures of Materiel Capability Performance

Pie Chart: Percentage Breakdown of Materiel Capability Performance

Green:
The project delivered the capability elements required by the revised Initial Materiel Release (IMR) date of 30 September 2009. The project is also on track to deliver all 22 Armed Reconnaissance Helicopters in the final configuration and have the required numbers of aircrew, groundcrew and technicians trained before the Final Materiel Release (FMR) date.

Amber:
Delivery of some long lead time Repairable Items (RIs) and Support and Test Equipment (S&TE) are currently forecast to occur after the FMR date. Commonwealth and contractor actively managing delivery of remaining RIs and S&TE items.

As the requirements for the Other DMO Fundamental Inputs to Capability elements are developed and contracted, the delivery of the required capabilities may not be able to be achieved by the FMR date.

Red:
N/A