Estimate $m | Actual $m | Variance $m | Variance Factor | Explanation |
|
|
| The end of year achievement was $70m, the major variation (from the $73m planned) was due to the delay of the EL/L-8222 Jammer Factory Acceptance Testing. This $5m payment will now occur in 2011-12. To offset this delayed payment, activities were brought forward from 2011-12, thus the underspend was reduced to ($3m). | |
(3.0) | Overseas Industry | |||
| Local Industry | |||
| Brought Forward | |||
| Cost Savings | |||
| FOREX Variation | |||
| Commonwealth Delays | |||
73.1 | 70.1 | (3.0) | Total Variance |