3.1  Design Review Progress

Review

Major System / Platform Variant

Original Planned

Current Planned

Achieved /Forecast

Variance (Months)

Notes

System Requirements

Phase 2.1

N/A

N/A

N/A

N/A

 

Phase 2.2

Feb 02

Feb 02

Feb 02

0

 

Phase 2.3

Jan 07

Jan 07

Jan 07

0

 

HACTS

Sep 04

Sep 04

Sep 04

0

 

Preliminary Design

Phase 2.1

N/A

N/A

N/A

N/A

 

Phase 2.2

Sep 02

Sep 02

Sep 02

0

 

Phase 2.3 (SDR)

Jan 07

Jan 07

Jan 07

0

 

HACTS

Jan 05

Jan 05

Jan 05

0

 

Critical Design

Phase 2.1

N/A

N/A

N/A

N/A

 

Phase 2.2

Mar 03

Mar 03

Mar 03

0

 

Phase 2.3

Jun 07

Jun 07

Jun 07

0

 

HACTS

Mar 05

Mar 05

Mar 05

0