Review | Major System / Platform Variant | Original Planned | Current Planned | Achieved /Forecast | Variance (Months) | Notes |
System Requirements | Phase 2.1 | N/A | N/A | N/A | N/A |
|
Phase 2.2 | Feb 02 | Feb 02 | Feb 02 | 0 |
| |
Phase 2.3 | Jan 07 | Jan 07 | Jan 07 | 0 |
| |
Sep 04 | Sep 04 | Sep 04 | 0 |
| ||
Preliminary Design | Phase 2.1 | N/A | N/A | N/A | N/A |
|
Phase 2.2 | Sep 02 | Sep 02 | Sep 02 | 0 |
| |
Phase 2.3 (SDR) | Jan 07 | Jan 07 | Jan 07 | 0 |
| |
Jan 05 | Jan 05 | Jan 05 | 0 |
| ||
Critical Design | Phase 2.1 | N/A | N/A | N/A | N/A |
|
Phase 2.2 | Mar 03 | Mar 03 | Mar 03 | 0 |
| |
Phase 2.3 | Jun 07 | Jun 07 | Jun 07 | 0 |
| |
Mar 05 | Mar 05 | Mar 05 | 0 |
|