3.2  Contractor Test and Evaluation Progress

Test and Evaluation

Major System / Platform Variant

Original Planned

Current Planned

Achieved /Forecast

Variance (Months)

Notes

System Integration

Phase 2.1

N/A

N/A

N/A

N/A

 

Phase 2.2 (First Article Contract / Project acceptance)

Feb 05

Jan 05

Jan 05

(1)

1

Phase 2.3 (System Integration Lab Test)

May 07

May 07

May 07

0

 

HACTS (Factory Acceptance Test)

May 06

May 06

May 06

0

 

Acceptance

Phase 2.1

N/A

N/A

N/A

N/A

 

Phase 2.2 (Aircraft Modification DMO Acceptance - A&B model)

Nov 05

Nov 05

Nov 05

0

 

Phase 2.3 (Aircraft Verification and Validation)

Sep 08

Sep 08

Aug 08

(1)

1

HACTS (Site Acceptance Test)

Jun 06

Jun 06

Jun 06

0

 

Notes

1

Modification of Validation and Verification aircraft completed earlier than anticipated.