Item | Original Planned | Achieved /Forecast | Variance (Months) | Variance Explanation / Implications |
Initial Materiel Release (IMR) | ||||
Phase 2.1 IMR | N/A | N/A | N/A |
|
Phase 2.2 IMR | N/A | Apr 07 | 0 |
|
Phase 2.3 IMR | N/A | Dec 08 | 0 |
|
N/A | Jul 06 | 0 |
| |
Materiel Release (MR) 2 | ||||
Phase 2.3 MR2 | Aug 11 | Aug 11 | 0 |
|
Phase 2.1 IOC | N/A | N/A | N/A |
|
Phase 2.2 IOC | Apr 07 | Apr 07 | 0 |
|
Phase 2.3 IOC | Nov 09 | Aug 11 | 21 | IOC requires the completion of Operational Testing and Evaluation (OT&E) and an Airworthiness Board for Supplemental Type Certification and Service Board Release by the RAAF. |
Jun 06 | Jul 06 | 1 | Delays in the development and issue of Site Acceptance Report. | |
Final Materiel Release (FMR) | ||||
Phase 2.1 FMR | N/A | N/A | N/A |
|
Phase 2.2 FMR | N/A | Dec 07 | 0 |
|
Phase 2.3 FMR | Jun 11 | Nov 11 | 5 | The delivery schedule for the required number of modified aircraft currently fails to meet the FMR milestone. Planned date has been amended to reflect updated Material Acquisition Agreement approved in June 2011. |
Aug 11 | Aug 11 | 0 |
| |
Phase 2.1 FOC | N/A | N/A | N/A |
|
Phase 2.2 FOC | Dec 07 | Dec 07 | 0 |
|
Phase 2.3 FOC | Aug 11 | Jun 12 | 10 | FOC requires the completion of OT&E and an Airworthiness Board for Supplemental Type Certification and Service Board Release by the RAAF. |
Mar 07 | Dec 11 | 55 | There is no identified HACTS FOC milestone; however project closure was scheduled for December 2009. The delivery of upgrades to the HACTS system to HUG 2.2 aircraft configuration have been completed. A further upgrade to reflect the HUG 2.3 aircraft configuration and address some HACTS training limitations will be progressed. | |
Schedule Status as at 30 Jun 11