2.2  Project Expenditure History

Date

Description

Base Date $m

Current $m

Contractor

Notes

2.2 Project Expenditure History

 

 

 

 

Prior to Jul 10

 

1,328.1

1,266.5

 

US Government

2

 

 

46.5

46.5

 

Other

3

 

 

1,374.6

 

1,313.0

 

 

FY to Jun 11

 

0.0

0.0

 

US Government

2

 

 

5.4

5.4

 

Other

3

 

 

5.4

 

5.4

 

 

Jun 11

Total Expenditure

1,380.0

 

1,313.4

 

 

 

 

 

 

 

 

 

Jun 11

Remaining Budget

484.4

 

530.5

 

 

 

 

 

 

 

 

 

Notes

1

Up until July 2010, indexation was applied to project budgets on a periodic basis. The cumulative impact of this approach was $103.3m. In addition to this amount, the impact on the project budget as a result of out-turning was a further $20.7m having been applied to the remaining life of the project.

2

For Base Date calculations for FMS cases, a consistent de-escalation factor has been applied to all projects which is derived from Defence's cost estimation methodology.

3

Other expenditure comprises: operating expenditure, contractors and other capital expenditure not attributable to the aforementioned top 5 contracts and minor contract expenditure.