2.4  Details of Project Major Contracts

Contractor

Signature Date

Price (Base) at

Type (Price Basis)

Form of Contract

Notes

Signature $m

30 Jun 11 $m

US Government

May 06

1,568.3

1,487.6

FMS

FMS

1

Notes

1

Original contract value based on accelerated schedule with some scope items not included in initial version of FMS Case. Seven case amendments have been made to date to capture these residual scope items.

Contractor

Quantities as at

Scope

Notes

Signature

30 Jun 11

US Government

4

4

C-17 Globemaster III Aircraft

 

Major equipment received and quantities to 30 Jun 11

Four aircraft accepted. Maintenance and Aircrew Training Systems and other engineering and maintenance arrangements established.