3.1  Design Review Progress

Review

Major System / Platform Variant

Original Planned

Current Planned

Achieved /Forecast

Variance (Months)

Notes

System Requirements

C-17 Globemaster III Aircraft

 

 

 

 

1

Australian Visual Database

 

Apr 08

Apr 08

0

 

Virtual Cargo Load Model

 

Aug 07

Aug 07

0

 

Cargo Compartment Trainer

 

Mar 11

Mar 11

0

2

Preliminary Design

C-17 Globemaster III Aircraft

 

 

 

 

1

Weapon System Trainer Simulated Avionics Package

 

Apr 07

Apr 07

0

 

Australian Visual Database

 

Nov 08

Dec 08

1

 

Virtual Cargo Load Model

 

Aug 07

Aug 07

0

 

Cargo Compartment Trainer

 

Mar 11

Mar 11

0

2

Critical Design

C-17 Globemaster III Aircraft

 

 

 

 

1

Weapon System Trainer Simulated Avionics Package

 

Aug 07

Aug 07

0

 

Australian Visual Database

 

Nov 08

Apr 09

5

 

Virtual Cargo Load Model

 

Nov 07

Nov 07

0

 

Cargo Compartment Trainer

 

Apr 11

Apr 11

0

2

Notes

1

C-17 Globemaster III Aircraft design reviews not required as it is Military Off-The-Shelf i.e. Mature Design with no ADF unique changes.

2

The inclusion of the C-17 Cargo Compartment Trainer in the FY 2010-11 summary is a result of the United States Air Force achieving contract signature with Boeing USA late February 2011.