4.1 Measures of Materiel Capability Performance

Pie Chart: Percentage Breakdown of Materiel Capability Performance

Green:

The project is currently meeting materiel capability requirements. These include, but are not limited to:

• Safely and effectively refuelling aircraft equipped with pod hose and drogue compatible refuelling systems;

• Ability to accept military and civil pallets and bulk cargo;

• Suitable military and civil communication and navigation suites; and

• Aircraft and through life support system capable of sustaining prescribed annual rate of effort.

Amber:

There is risk to meeting all materiel capability requirements for FOC due to acceptance of aircraft in an initial configuration and the risk of successful remediation of all non-conformances and improvements to the Aerial Refuelling Boom System.

Red:

N/A