2.1 Project Budget History

Date

Description

Base Date $m

Current $m

Contractor

Notes

2.1 Project Budget History

 

 

 

 

 

Dec 97

Original Approved

1,266.0

 

1,266.0

 

1

Nov 98

Real Variation - Budgetary

(0.1)

(0.1)

 

 

2

 

Adjustments

 

 

 

 

 

Jul 99

Real Variation - Transfer

(152.6)

(152.6)

 

 

3

Aug 04

Real Variation - Budgetary

(0.7)

(0.7)

 

 

4

 

Adjustments

 

 

 

 

 

Jun 11

Price Indexation

 

 

230.3

 

5

Jun 11

Exchange Variation

 

 

186.0

 

 

Jun 11

Total Budget

1,112.6

 

1,528.9