3.1 Design Review Progress

Review

Major System / Platform Variant

Original
Planned

Current
Planned

Achieved
/Forecast

Variance
(Months)

Notes

System
Requirements

Completion of all Software
Specification Reviews

Aug 00

Aug 00

May 01

9

1

Preliminary
Design

Completion of all Preliminary
Design Reviews

Oct 00

Oct 00

May 01

7

1

Critical
Design

Completion of all Critical Design
Reviews (Critical)

Apr 01

Nov 06

Apr 07

72

1

Notes




1

Software development and design was delayed due to Australian Defence Industry (now Thales Australia) repatriating the Combat System Design Authority role from Lockheed Martin in early 2001 and implementing the Australian Distributed Architecture Combat System. Thales then elected, as allowed by the Prime Contract, to deliver the contracted capability in three software baselines for technical risk mitigation. 

Critical Design Review to Baseline Build 2 software completed in December 2006. Critical Design Review for Baseline Build 3 software completed in April 2007.