3.2 Contractor Test and Evaluation Progress

Test and
Evaluation

Major System / Platform Variant

Original
Planned

Current
Planned

Achieved
/Forecast

Variance
(Months)

Notes

System
Integration

SRP1D Prototype Modifications - 
DMO Acceptance

Jan 06

N/A

Jan 06

0

 

SRP2 Prototype Modifications   - 
DMO Acceptance

Dec 07

N/A

Feb 08

2

1

Acceptance

N/A

N/A

N/A

N/A

N/A

 

Notes

1

The first SRP2 prototype aircraft was delayed by two months due to emergent issues discovered during prototype rebuild.